United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMBattery storage project AI2-002, Washington County
Battery storage project AI2-002, Washington County is a 150 MW battery storage request in interconnection study in the PJM interconnection queue, in Washington County, Virginia, connecting to APS.
Queue statusIn planning
- PlanningQueued Oct 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-002
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Vanceville 138 kV
- Location
- Washington County, Virginia
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 1 October 2022
- Proposed online date
- May 2028
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Battery storage project AH2-072, Washington CountyBattery storage · 62.1 MW · in study
- Wolf Hills Energy PlantGas · 19.0 MW · built
- Wolf Hills Energy PlantGas · 15.0 MW · built
- Other project 185, Washington CountyOther · 250 MW · withdrawn
- Battery storage project AH1-063, Washington CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem