GAS · PJMWolf Hills Energy Plant
Wolf Hills Energy Plant is a 19.0 MW gas request built and operating in the PJM interconnection queue, in Washington County, Virginia, connecting to AEP.
Request details
- Queue ID
- AE1-178
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Wolf Hills 138 kV
- Location
- Washington County, Virginia
- Technology
- Gas: 19.0 MW
- Total requested
- 19.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 25 September 2018
- Proposed online date
- December 2021
- Came online
- May 2021
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Battery storage project AI2-002, Washington CountyBattery storage · 150 MW · in study
- Battery storage project AH2-072, Washington CountyBattery storage · 62.1 MW · in study
- Wolf Hills Energy PlantGas · 15.0 MW · built
- Other project 185, Washington CountyOther · 250 MW · withdrawn
- Battery storage project AH1-063, Washington CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem