United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMBattery storage project AI2-231, Prince William County
Battery storage project AI2-231, Prince William County is a 120 MW battery storage request in interconnection study in the PJM interconnection queue, in Prince William County, Virginia, connecting to Dominion.
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-231
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Gainesville-Loudoun 230 kV
- Location
- Prince William County, Virginia
- Technology
- Battery: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- October 2023
Location
Marker shows the centre of Prince William County; the queue data does not give exact sites.
Other requests in Prince William County
- Battery storage project AH2-034, Prince William CountyBattery storage · 100 MW · in study
- Battery storage project AH2-035, Prince William CountyBattery storage · 100 MW · in study
- Battery storage project AH2-032, Prince William CountyBattery storage · 60.0 MW · in study
- Battery storage project AH2-033, Prince William CountyBattery storage · 60.0 MW · in study
- Battery storage project AH2-061, Prince William CountyBattery storage · 55.0 MW · in study
- Battery storage project AH2-060, Prince William CountyBattery storage · 55.0 MW · in study
- Battery storage project AH2-059, Prince William CountyBattery storage · 30.0 MW · in study
- Battery storage project AH2-058, Prince William CountyBattery storage · 30.0 MW · in study
- Reid Energy CenterBattery storage · 20.0 MW · in study
- Railroad Energy CenterBattery storage · 20.0 MW · in study
- Bethlehem Energy CenterBattery storage · 20.0 MW · in study
- Possum Point Unit 6Gas · 28.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem