United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMHarwood Power
Harwood Power is a 100 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in King George County, Virginia, connecting to Dominion.
Queue statusConsented
- PlanningQueued Oct 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-013
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Arnold's Corner-Dahlgren 230 kV
- Location
- King George County, Virginia
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 15 October 2019
- Proposed online date
- October 2029
Location
Marker shows the centre of King George County; the queue data does not give exact sites.
Other requests in King George County
- Gibson Solar ISolar · 100 MW · agreement signed
- Gibson Solar ISolar · 34.0 MW · agreement signed
- Battery storage project AI2-456, King George CountyBattery storage · 150 MW · in study
- Battery storage project AH2-144, King George CountyBattery storage · 150 MW · in study
- Battery storage project AH2-145, King George CountyBattery storage · 52.3 MW · in study
- King George Renewable Energy FacilityOther · 9.8 MW · built
- Gas project T149, King George CountyGas · 580 MW · withdrawn
- Battery storage project AG1-019, King George CountyBattery storage · 100 MW · withdrawn
- Battery storage project AG2-303, King George CountyBattery storage · 100 MW · withdrawn
- Solar project AG2-199, King George CountySolar · 55.0 MW · withdrawn
- Solar project AB2-072, King George CountySolar · 18.0 MW · withdrawn
- Battery storage project AG1-212, King George CountyBattery storage · 7.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem