🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Harwood Power

Harwood Power is a 100 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in King George County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued Oct 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-013
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Arnold's Corner-Dahlgren 230 kV
Location
King George County, Virginia
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
15 October 2019
Proposed online date
October 2029

Location

Marker shows the centre of King George County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in King George County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem