Battery storage project AI2-456, King George County

Battery storage project AI2-456, King George County is a 150 MW battery storage request in interconnection study in the PJM interconnection queue, in King George County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-456
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Birchwood - Fines Corner 230 kV
Location
King George County, Virginia
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
11 March 2023
Proposed online date
September 2027

Location

Marker shows the centre of King George County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in King George County