United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Prospect Power

Prospect Power is a 200 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Rockingham County, Virginia, connecting to Dominion.

Queue statusConsented
  1. PlanningQueued May 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-028
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Endless Caverns 115 kV
Location
Rockingham County, Virginia
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
13 May 2019
Proposed online date
February 2026

Location

Marker shows the centre of Rockingham County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Rockingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem