🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AG2-360, Smyth County

Battery storage project AG2-360, Smyth County is a 250 MW battery storage request in interconnection study in the PJM interconnection queue, in Smyth County, Virginia, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-360
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Laurel Creek Energy Storage LLC
Connection point (POI)
Broadford 138 kV
Location
Smyth County, Virginia
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
11 February 2025
Proposed online date
November 2024

Location

Marker shows the centre of Smyth County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Smyth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem