🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Saltville-Holston 34.5kV Solar Facility

Saltville-Holston 34.5kV Solar Facility is a 5.0 MW solar request withdrawn in the PJM interconnection queue, in Smyth County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2015 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-011
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Saltville-Holstone 34.5kV - Phase II
Location
Smyth County, Virginia
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
1 December 2015
Proposed online date
December 2017
Withdrawn
February 2019

Location

Marker shows the centre of Smyth County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Smyth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem