SOLAR + STORAGE Β· PJMSolar + storage project AG2-597, Smyth County
Solar + storage project AG2-597, Smyth County is a 200 MW solar + storage request withdrawn in the PJM interconnection queue, in Smyth County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-597
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Broadford 138 kV
- Location
- Smyth County, Virginia
- Technology
- Solar: 200 MW Β· Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- October 2025
- Withdrawn
- December 2024
Location
Marker shows the centre of Smyth County; the queue data does not give exact sites.
Other requests in Smyth County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem