Battery storage project AG1-314, Smyth County

Battery storage project AG1-314, Smyth County is a 100 MW battery storage request withdrawn in the PJM interconnection queue, in Smyth County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedDec 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-314
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Rural Retreat 138 kV
Location
Smyth County, Virginia
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 September 2020
Proposed online date
June 2024
Withdrawn
December 2020

Location

Marker shows the centre of Smyth County; the queue data does not give exact sites.