Withdrawn queue requests in SPP (Southwest Power Pool) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7013.1 GW
Active in queue9,029 MW44 requests
Agreement signed3,459 MW19 requests
Withdrawn7013.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

70 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2021-072, Mercer County
Solar
600 MWWithdrawn / abandoned Mercer, NDSPP May 2021target 2027
Onshore wind project GEN-2021-007, Knox County
Onshore wind
600 MWWithdrawn / abandoned Knox, NESPP May 20212025
Solar project GEN-2021-074, Prowers County
Solar
500 MWWithdrawn / abandoned Prowers, COSPP May 2021target 2026
Gas project GEN-2021-095, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 2021target 2028
Gas project GEN-2021-094, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 20212025
Onshore wind project GEN-2021-071, Noble County
Onshore wind
403 MWWithdrawn / abandoned Noble, OKSPP Apr 2021target 2027
Onshore wind project GEN-2021-046, Prowers County
Onshore wind
400 MWWithdrawn / abandoned Prowers, COSPP Apr 2021target 2026
Solar project GEN-2021-089, Hockley County
Solar
400 MWWithdrawn / abandoned Hockley, TXSPP Apr 2021target 2026
Onshore wind project GEN-2021-058, Madison County
Onshore wind
300 MWWithdrawn / abandoned Madison, NESPP Apr 2021target 2026
Onshore wind project GEN-2021-044, Dundy County
Onshore wind
300 MWWithdrawn / abandoned Dundy, NESPP Apr 2021target 2026
Solar + storage project GEN-2021-075, Camp County
Solar + storage
300 MWWithdrawn / abandoned Camp, TXSPP May 2021target 2027
Onshore wind project GEN-2021-060, Lancaster County
Onshore wind
300 MWWithdrawn / abandoned Lancaster, NESPP Apr 2021target 2027
Wind + storage project GEN-2021-097, Roosevelt County
Wind + storage
300 MWWithdrawn / abandoned Roosevelt, NMSPP May 2021target 2026
Onshore wind project GEN-2021-045, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, KSSPP Apr 2021target 2026
Solar + storage project GEN-2021-004, Carter County
Solar + storage
250 MWWithdrawn / abandoned Carter, OKSPP Apr 2021target 2027
Onshore wind project GEN-2021-099, Ellis County
Onshore wind
250 MWWithdrawn / abandoned Ellis, OKSPP Apr 20212025
Onshore wind project GEN-2021-037, Perkins County
Onshore wind
244 MWWithdrawn / abandoned Perkins, NESPP May 2021target 2026
Solar project GEN-2021-055, Titus County
Solar
240 MWWithdrawn / abandoned Titus, TXSPP Apr 2021target 2026
Solar project GEN-2021-073, Lancaster County
Solar
240 MWWithdrawn / abandoned Lancaster, NESPP May 2021target 2027
Battery storage project GEN-2021-009, Beadle County
Battery storage
225 MWWithdrawn / abandoned Beadle, SDSPP May 2021target 2026
Solar project GEN-2021-010, Beckham County
Solar
208 MWWithdrawn / abandoned Beckham, OKSPP Apr 2021target 2029
Solar project GEN-2021-014, Beckham County
Solar
208 MWWithdrawn / abandoned Beckham, OKSPP Apr 2021target 2029
Solar project GEN-2021-028, Woodward County
Solar
204 MWWithdrawn / abandoned Woodward, OKSPP May 2021target 2027
Battery storage project GEN-2021-012, Beckham County
Battery storage
203 MWWithdrawn / abandoned Beckham, OKSPP Apr 2021target 2029
Onshore wind project GEN-2021-024, Lamoure County
Onshore wind
203 MWWithdrawn / abandoned Lamoure, NDSPP May 2021target 2026
Battery storage project GEN-2021-031, Choctaw County
Battery storage
202 MWWithdrawn / abandoned Choctaw, OKSPP May 2021target 2026
Solar project GEN-2021-026, Barton County
Solar
200 MWWithdrawn / abandoned Barton, MOSPP May 2021target 2027
Solar project GEN-2021-105, Lancaster County
Solar
200 MWWithdrawn / abandoned Lancaster, NESPP May 2021target 2027
Solar + storage project GEN-2021-065, Pittsburg County
Solar + storage
200 MWWithdrawn / abandoned Pittsburg, OKSPP Apr 2021target 2026
Solar project GEN-2021-050, Henry County
Solar
200 MWWithdrawn / abandoned Henry, MOSPP Apr 2021target 2028
Solar project GEN-2021-008, Mckenzie County
Solar
200 MWWithdrawn / abandoned Mckenzie, NDSPP May 2021target 2030
Solar + storage project GEN-2021-084, Kearny County
Solar + storage
180 MWWithdrawn / abandoned Kearny, KSSPP Apr 2021target 2028
Solar + storage project GEN-2021-086, Howard County
Solar + storage
165 MWWithdrawn / abandoned Howard, ARSPP Apr 2021target 2027
Wind + storage project GEN-2021-098, Dewey County
Wind + storage
160 MWWithdrawn / abandoned Dewey, OKSPP May 2021target 2026
Solar + storage project GEN-2021-078, Finney County
Solar + storage
160 MWWithdrawn / abandoned Finney, KSSPP Apr 2021target 2028
Solar + storage project GEN-2021-066, Pittsburg County
Solar + storage
150 MWWithdrawn / abandoned Pittsburg, OKSPP Apr 2021target 2026
Solar project GEN-2021-091, Pontotoc County
Solar
150 MWWithdrawn / abandoned Pontotoc, OKSPP Apr 2021target 2027
Solar project GEN-2021-054, Terry County
Solar
150 MWWithdrawn / abandoned Terry, TXSPP Apr 20212025
Solar project GEN-2021-032, Choctaw County
Solar
150 MWWithdrawn / abandoned Choctaw, OKSPP May 2021target 2026
Solar + storage project GEN-2021-079, Delaware County
Solar + storage
140 MWWithdrawn / abandoned Delaware, OKSPP Apr 2021target 2026
Solar project GEN-2021-059, Jasper County
Solar
130 MWWithdrawn / abandoned Jasper, MOSPP Apr 20212025
Battery storage project GEN-2021-SR5, Hansford County
Battery storage
126 MWWithdrawn / abandoned Hansford, TXSPP May 2021target 2023
Solar project GEN-2021-062, Lea County
Solar
110 MWWithdrawn / abandoned Lea, NMSPP Apr 20212025
Solar project GEN-2021-106, Thayer County
Solar
102 MWWithdrawn / abandoned Thayer, NESPP May 2021target 2026
Solar project GEN-2021-061, Sedgwick County
Solar
100 MWWithdrawn / abandoned Sedgwick, KSSPP Apr 20212025
Solar + storage project GEN-2021-087, Seward County
Solar + storage
100 MWWithdrawn / abandoned Seward, KSSPP Apr 2021target 2028
Battery storage project GEN-2022-001, Rogers County
Battery storage
100 MWWithdrawn / abandoned Rogers, OKSPP Dec 2021target 2027
Solar + storage project GEN-2021-080, Lea County
Solar + storage
100 MWWithdrawn / abandoned Lea, NMSPP Apr 20212024
Solar + storage project GEN-2021-085, Ford County
Solar + storage
100 MWWithdrawn / abandoned Ford, KSSPP Apr 2021target 2027
Battery storage project GEN-2021-092, Hansford County
Battery storage
100 MWWithdrawn / abandoned Hansford, TXSPP Apr 2021target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)