πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· SPP

Solar project GEN-2021-062, Lea County

Solar project GEN-2021-062, Lea County is a 110 MW solar request withdrawn in the SPP interconnection queue, in Lea County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-062
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Roadrunner 115 kV Substation
Location
Lea County, New Mexico
Technology
Solar: 110 MW
Total requested
110 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2021
Proposed online date
December 2025
Came online
December 2025
Withdrawn
July 2023

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem