πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· SPP

Battery storage project GEN-2021-092, Hansford County

Battery storage project GEN-2021-092, Hansford County is a 100 MW battery storage request withdrawn in the SPP interconnection queue, in Hansford County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-092
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Xcel Hansford 115kV substation
Location
Hansford County, Texas
Technology
Battery: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 April 2021
Proposed online date
March 2026
Withdrawn
December 2022

Location

Marker shows the centre of Hansford County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hansford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem