United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

SOLAR Β· SPP

Solar project GEN-2021-091, Pontotoc County

Solar project GEN-2021-091, Pontotoc County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Pontotoc County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedNov 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-091
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
OG&E's Blue River 138kV Substation
Location
Pontotoc County, Oklahoma
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2021
Proposed online date
October 2027
Withdrawn
November 2022

Location

Marker shows the centre of Pontotoc County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Pontotoc County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem