ONSHORE WIND Β· SPP

Onshore wind project GEN-2014-014, Pontotoc County

Onshore wind project GEN-2014-014, Pontotoc County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Pontotoc County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2014 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2014-014
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Blue River 138 kV
Location
Pontotoc County, Oklahoma
Technology
Wind: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
20 June 2014
Proposed online date
December 2017
Withdrawn
September 2014

Location

Marker shows the centre of Pontotoc County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Pontotoc County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem