United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
SOLAR Β· SPPSolar project GEN-2023-152, Pontotoc County
Solar project GEN-2023-152, Pontotoc County is a 140 MW solar request withdrawn in the SPP interconnection queue, in Pontotoc County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-152
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Allen NG4 138 kV Substation
- Location
- Pontotoc County, Oklahoma
- Technology
- Solar: 140 MW
- Total requested
- 140 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- September 2026
- Withdrawn
- March 2024
Location
Marker shows the centre of Pontotoc County; the queue data does not give exact sites.
Other requests in Pontotoc County
- Onshore wind project GEN-2016-102, Pontotoc CountyOnshore wind Β· 148 MW Β· agreement signed
- Battery storage project ERAS-2025-022, Pontotoc CountyBattery storage Β· 123 MW Β· in study
- Solar project GEN-2021-091, Pontotoc CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2014-014, Pontotoc CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem