SOLAR Β· SPP

Solar project GEN-2021-028, Woodward County

Solar project GEN-2021-028, Woodward County is a 204 MW solar request withdrawn in the SPP interconnection queue, in Woodward County, Oklahoma, connecting to WFEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-028
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Western Farmers 138kV Mooreland Substation
Location
Woodward County, Oklahoma
Technology
Solar: 204 MW
Total requested
204 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
14 May 2021
Proposed online date
December 2027
Withdrawn
September 2024

Location

Marker shows the centre of Woodward County; the queue data does not give exact sites.