United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

BATTERY STORAGE Β· SPP

Battery storage project GEN-2021-012, Beckham County

Battery storage project GEN-2021-012, Beckham County is a 203 MW battery storage request withdrawn in the SPP interconnection queue, in Beckham County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-012
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Border 345 kV interconnection substation
Location
Beckham County, Oklahoma
Technology
Battery: 203 MW
Total requested
203 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 April 2021
Proposed online date
December 2029
Withdrawn
July 2025

Location

Marker shows the centre of Beckham County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Beckham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem