United States › Grid › Interconnection queues › Oklahoma
SOLAR · SPPSolar project GEN-2024-154, Beckham County
Solar project GEN-2024-154, Beckham County is a 200 MW solar request in interconnection study in the SPP interconnection queue, in Beckham County, Oklahoma, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-154
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Chisholm 345 kV Substation
- Location
- Beckham County, Oklahoma
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Beckham County; the queue data does not give exact sites.
Other requests in Beckham County
- Onshore wind project GEN-2006-035, Beckham CountyOnshore wind · 132 MW · built
- Onshore wind project GEN-2006-002, Beckham CountyOnshore wind · 101 MW · built
- Onshore wind project GEN-2006-043, Beckham CountyOnshore wind · 99.0 MW · built
- Onshore wind project GEN-2011-049, Beckham CountyOnshore wind · 251 MW · withdrawn
- Solar project GEN-2021-010, Beckham CountySolar · 208 MW · withdrawn
- Solar project GEN-2021-014, Beckham CountySolar · 208 MW · withdrawn
- Battery storage project GEN-2021-012, Beckham CountyBattery storage · 203 MW · withdrawn
- Onshore wind project GEN-2015-071, Beckham CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2008-039, Beckham CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2009-070, Beckham CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2010-018, Beckham CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project GEN-2009-016, Beckham CountyOnshore wind · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem