United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2015-071, Beckham County
Onshore wind project GEN-2015-071, Beckham County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Beckham County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2015 (completed)
- Withdrawn / abandonedSep 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2021 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2015-071
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Chisholm 345kV
- Location
- Beckham County, Oklahoma
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- TERMINATED
- Queue status
- Withdrawn
- Entered queue
- 9 October 2015
- Proposed online date
- December 2021
- Came online
- December 2021
- Withdrawn
- September 2019
Location
Marker shows the centre of Beckham County; the queue data does not give exact sites.
Other requests in Beckham County
- Solar project GEN-2024-154, Beckham CountySolar Β· 200 MW Β· in study
- Onshore wind project GEN-2006-035, Beckham CountyOnshore wind Β· 132 MW Β· built
- Onshore wind project GEN-2006-002, Beckham CountyOnshore wind Β· 101 MW Β· built
- Onshore wind project GEN-2006-043, Beckham CountyOnshore wind Β· 99.0 MW Β· built
- Onshore wind project GEN-2011-049, Beckham CountyOnshore wind Β· 251 MW Β· withdrawn
- Solar project GEN-2021-010, Beckham CountySolar Β· 208 MW Β· withdrawn
- Solar project GEN-2021-014, Beckham CountySolar Β· 208 MW Β· withdrawn
- Battery storage project GEN-2021-012, Beckham CountyBattery storage Β· 203 MW Β· withdrawn
- Onshore wind project GEN-2008-039, Beckham CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2009-070, Beckham CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2010-018, Beckham CountyOnshore wind Β· 101 MW Β· withdrawn
- Onshore wind project GEN-2009-016, Beckham CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem