SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2021-079, Delaware County

Solar + storage project GEN-2021-079, Delaware County is a 140 MW solar + storage request withdrawn in the SPP interconnection queue, in Delaware County, Oklahoma, connecting to GRDA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-079
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
GRDA
Connection point (POI)
Flint Creek to Tonnece 345 kV
Location
Delaware County, Oklahoma
Technology
Solar: 140 MW Β· Battery
Total requested
140 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 April 2021
Proposed online date
December 2026
Withdrawn
July 2023

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Delaware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem