πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2013-036, Delaware County

Onshore wind project GEN-2013-036, Delaware County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Delaware County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2013 (completed)
  2. Withdrawn / abandonedFeb 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2013-036
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Delaware Substation 345 kv
Location
Delaware County, Oklahoma
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
20 December 2013
Proposed online date
December 2016
Withdrawn
February 2014

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Delaware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem