SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2021-067, Delaware County

Solar + storage project GEN-2021-067, Delaware County is a 100 MW solar + storage request withdrawn in the SPP interconnection queue, in Delaware County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-067
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Tap Grove - Jay 138kV
Location
Delaware County, Oklahoma
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 April 2021
Proposed online date
October 2026
Withdrawn
July 2023

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.