United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2023-162, Delaware County
Solar + storage project GEN-2023-162, Delaware County is a 100 MW solar + storage request withdrawn in the SPP interconnection queue, in Delaware County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-162
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Grove - Jay 138 kV Line
- Location
- Delaware County, Oklahoma
- Technology
- Solar: 100 MW Β· Battery
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- October 2027
- Withdrawn
- March 2024
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Other requests in Delaware County
- Onshore wind project GEN-2013-036, Delaware CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2023-138, Delaware CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2023-072, Delaware CountyOnshore wind Β· 250 MW Β· withdrawn
- Solar + storage project GEN-2021-079, Delaware CountySolar + storage Β· 140 MW Β· withdrawn
- Solar + storage project GEN-2021-067, Delaware CountySolar + storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem