United States βΊ Grid βΊ Interconnection queues βΊ Kansas
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2021-084, Kearny County
Solar + storage project GEN-2021-084, Kearny County is a 180 MW solar + storage request withdrawn in the SPP interconnection queue, in Kearny County, Kansas, connecting to SUNC.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandonedJul 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2021-084
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Williamson - Fletcher 115kV
- Location
- Kearny County, Kansas
- Technology
- Solar: 180 MW Β· Battery
- Total requested
- 180 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 April 2021
- Proposed online date
- December 2028
- Withdrawn
- July 2023
Location
Marker shows the centre of Kearny County; the queue data does not give exact sites.
Other requests in Kearny County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem