United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2023-172, Kearny County

Onshore wind project GEN-2023-172, Kearny County is a 200 MW onshore wind request in interconnection study in the SPP interconnection queue, in Kearny County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-172
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Holcomb 345 kV
Location
Kearny County, Kansas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
December 2029

Location

Marker shows the centre of Kearny County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Kearny County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem