United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

ONSHORE WIND Β· SPP

Onshore wind project GEN-2021-037, Perkins County

Onshore wind project GEN-2021-037, Perkins County is a 244 MW onshore wind request withdrawn in the SPP interconnection queue, in Perkins County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-037
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
NPPD Sidney to Keystone 345 kV Line
Location
Perkins County, Nebraska
Technology
Wind: 244 MW
Total requested
244 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
14 May 2021
Proposed online date
December 2026
Withdrawn
September 2024

Location

Marker shows the centre of Perkins County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Perkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem