SOLAR Β· SPP

Solar project GEN-2021-061, Sedgwick County

Solar project GEN-2021-061, Sedgwick County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Sedgwick County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-061
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Gordan Evans 138 kV Substation
Location
Sedgwick County, Kansas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2021
Proposed online date
December 2025
Came online
December 2025
Withdrawn
September 2024

Location

Marker shows the centre of Sedgwick County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Sedgwick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem