Solar project GEN-2022-004, Sedgwick County

Solar project GEN-2022-004, Sedgwick County is a 33.0 MW solar request in interconnection study in the SPP interconnection queue, in Sedgwick County, Kansas, connecting to WERE.

Queue statusIn planning
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-004
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Murray Gill 138 kV Substation
Location
Sedgwick County, Kansas
Technology
Solar: 33.0 MW
Total requested
33.0 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
26 May 2022
Proposed online date
December 2028

Location

Marker shows the centre of Sedgwick County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Sedgwick County