SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2023-186, Sedgwick County

Solar + storage project GEN-2023-186, Sedgwick County is a 200 MW solar + storage request withdrawn in the SPP interconnection queue, in Sedgwick County, Kansas, connecting to Evergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-186
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Evergy
Connection point (POI)
Murray Gill 138 kV Substation
Location
Sedgwick County, Kansas
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
August 2028
Withdrawn
March 2024

Location

Marker shows the centre of Sedgwick County; the queue data does not give exact sites.