Solar project GEN-2021-054, Terry County

Solar project GEN-2021-054, Terry County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Terry County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-054
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Flatlands 115 kV Substation
Location
Terry County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2021
Proposed online date
December 2025
Came online
December 2025
Withdrawn
July 2023

Location

Marker shows the centre of Terry County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Terry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem