United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· SPPSolar project GEN-2016-077, Terry County
Solar project GEN-2016-077, Terry County is a 54.0 MW solar request withdrawn in the SPP interconnection queue, in Terry County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2016 (completed)
- Withdrawn / abandonedSep 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2016-077
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Lakeview-Brownfield 69kV line
- Location
- Terry County, Texas
- Technology
- Solar: 54.0 MW
- Total requested
- 54.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 June 2016
- Proposed online date
- December 2022
- Withdrawn
- September 2020
Location
Marker shows the centre of Terry County; the queue data does not give exact sites.
Other requests in Terry County
- Solar project GEN-2017-187, Terry CountySolar Β· 150 MW Β· agreement signed
- Onshore wind project GEN-2020-067, Terry CountyOnshore wind Β· 353 MW Β· in study
- Solar project GEN-2020-068, Terry CountySolar Β· 400 MW Β· withdrawn
- Solar project GEN-2021-054, Terry CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2007-004, Terry CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2006-030, Terry CountyOnshore wind Β· 150 MW Β· withdrawn
- Solar project GEN-2016-090, Terry CountySolar Β· 100 MW Β· withdrawn
- Solar project GEN-2014-044, Terry CountySolar Β· 50.0 MW Β· withdrawn
- Battery storage project GEN-2018-086, Terry CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem