United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Iowa, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown27761.2 GW
Active in queue23.7 GW120 requests
Agreement signed1,592 MW15 requests
Withdrawn27761.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

277 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Other project PQ0002, Cerro Gordo County
Other
2,000 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2015target 2021
Onshore wind project J116, Hancock County
Onshore wind
999 MWWithdrawn / abandoned Hancock, IAMISO Feb 2010target 2013
Gas project E0025, Linn County
Gas Β· Interstate Power and Light Company (IPL)
987 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Coal project G718, Wapello County
Coal
900 MWWithdrawn / abandoned Wapello, IAMISO Dec 2006target 2009
Gas project J355, Adair County
Gas
810 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2017
Gas project J363, Pottawattamie County
Gas
810 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2016
Coal project G589, Black Hawk County
Coal
750 MWWithdrawn / abandoned Black Hawk, IAMISO Jan 2006target 2006
Linn County Generating Facility
Nuclear Β· NextEra Energy Resources Development, LLC
676 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Other project G220, Buchanan County
Other
650 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2002target 2004
Gas project G219, Johnson County
Gas
650 MWWithdrawn / abandoned Johnson, IAMISO Apr 2002target 2006
Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
640 MWWithdrawn / abandoned Linn, IAMISO Sep 2021target 2023
Other project G129, Wapello County
Other
600 MWWithdrawn / abandoned Wapello, IAMISO Sep 2001target 2007
Gas project G181, Buchanan County
Gas
600 MWWithdrawn / abandoned Buchanan, IAMISO Mar 2002target 2004
Coal project G720, Marshall County
Coal
600 MWWithdrawn / abandoned Marshall, IAMISO Dec 2006target 2012
Gas project G182, Buchanan County
Gas
600 MWWithdrawn / abandoned Buchanan, IAMISO Mar 2002target 2004
Gas project G180, Marshall County
Gas
600 MWWithdrawn / abandoned Marshall, IAMISO Mar 2002target 2004
Other project G128, Marshall County
Other
600 MWWithdrawn / abandoned Marshall, IAMISO Sep 2001target 2003
Other project G127, Des Moines County
Other
600 MWWithdrawn / abandoned Des Moines, IAMISO Sep 2001target 2003
Gas project G179, Clinton County
Gas
600 MWWithdrawn / abandoned Clinton, IAMISO Mar 2002target 2002
Other project G178, Clinton County
Other
600 MWWithdrawn / abandoned Clinton, IAMISO Mar 2002target 2003
Other project G187, Muscatine County
Other
600 MWWithdrawn / abandoned Muscatine, IAMISO Apr 2002target 2003
Coal project G719, Wapello County
Coal
600 MWWithdrawn / abandoned Wapello, IAMISO Dec 2006target 2010
Onshore wind project J462, Emmet County
Onshore wind
598 MWWithdrawn / abandoned Emmet, IAMISO May 2015target 2016
Gas project G174, Cerro Gordo County
Gas
550 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2002target 2003
Onshore wind project R50, Washington County
Onshore wind
501 MWWithdrawn / abandoned Washington, IAMISO Feb 2008target 2010
Onshore wind project G973, Washington County
Onshore wind
501 MWWithdrawn / abandoned Washington, IAMISO Feb 2008target 2011
Other project G158, Linn County
Other
500 MWWithdrawn / abandoned Linn, IAMISO Nov 2001target 2003
Onshore wind project J439, Emmet County
Onshore wind
500 MWWithdrawn / abandoned Emmet, IAMISO Mar 2015target 2016
Other project G156, Cerro Gordo County
Other
500 MWWithdrawn / abandoned Cerro Gordo, IAMISO Nov 2001target 2005
Onshore wind project J154, Washington County
Onshore wind
500 MWWithdrawn / abandoned Washington, IAMISO Jun 2010target 2011
Other project G157, Linn County
Other
500 MWWithdrawn / abandoned Linn, IAMISO Nov 2001target 2003
Onshore wind project J192, Washington County
Onshore wind
500 MWWithdrawn / abandoned Washington, IAMISO Jan 2011target 2012
Other project G159, Buchanan County
Other
500 MWWithdrawn / abandoned Buchanan, IAMISO Nov 2001target 2003
Onshore wind project R52, Adair County
Onshore wind
500 MWWithdrawn / abandoned Adair, IAMISO Mar 2008target 2010
Onshore wind project J501, Hancock County
Onshore wind
500 MWWithdrawn / abandoned Hancock, IAMISO Nov 2015target 2017
Gas project J364, Adair County
Gas
464 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2016
Gas project J365, Pottawattamie County
Gas
464 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2018
Solar project J3998, Cerro Gordo County
Solar
450 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2025target 2030
Onshore wind project J578, Audubon County
Onshore wind
400 MWWithdrawn / abandoned Audubon, IAMISO May 2016target 2018
Onshore wind project J1427, Benton County
Onshore wind
400 MWWithdrawn / abandoned Benton, IAMISO Apr 2019target 2022
Onshore wind project G972, Fayette County
Onshore wind
400 MWWithdrawn / abandoned Fayette, IAMISO Feb 2008target 2010
Battery storage project J3022, Taylor County
Battery storage
400 MWWithdrawn / abandoned Taylor, IAMISO Sep 2022target 2026
Onshore wind project J1341, Buchanan County
Onshore wind
398 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2019target 2022
Other project G126, Des Moines County
Other
325 MWWithdrawn / abandoned Des Moines, IAMISO Sep 2001
Other project G125, Clinton County
Other
325 MWWithdrawn / abandoned Clinton, IAMISO Sep 2001
Onshore wind project J342, Buchanan County
Onshore wind
305 MWWithdrawn / abandoned Buchanan, IAMISO May 2014target 2015
Onshore wind project J2481, Pocahontas County
Onshore wind
300 MWWithdrawn / abandoned Pocahontas, IAMISO Sep 2022target 2030
Onshore wind project J410, Fayette County
Onshore wind
300 MWWithdrawn / abandoned Fayette, IAMISO Nov 2014target 2016
Onshore wind project G957, Emmet County
Onshore wind
300 MWWithdrawn / abandoned Emmet, IAMISO Jan 2008target 2010
Onshore wind project J095, Cerro Gordo County
Onshore wind
300 MWWithdrawn / abandoned Cerro Gordo, IAMISO Oct 2009target 2010
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)