United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J2481, Pocahontas County
Onshore wind project J2481, Pocahontas County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Pocahontas County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2481
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- Webster-Irvington 345kV
- Location
- Pocahontas County, Iowa
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 September 2022
- Proposed online date
- October 2030
- Withdrawn
- October 2025
Location
Marker shows the centre of Pocahontas County; the queue data does not give exact sites.
Other requests in Pocahontas County
- Solar project J3137, Pocahontas CountySolar Β· 156 MW Β· in study
- Onshore wind project R15, Pocahontas CountyOnshore wind Β· 80.0 MW Β· built
- Other project GI-1201, Pocahontas CountyOther Β· 7.0 MW Β· built
- Onshore wind project T93, Pocahontas CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project T92, Pocahontas CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project J1978, Pocahontas CountyOnshore wind Β· 175 MW Β· withdrawn
- Onshore wind project G315, Pocahontas CountyOnshore wind Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem