United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project R15, Pocahontas County
Onshore wind project R15, Pocahontas County is a 80.0 MW onshore wind request built and operating in the MISO interconnection queue, in Pocahontas County, Iowa.
Request details
- Queue ID
- R15
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Pomeroy 161 kV substation
- Location
- Pocahontas County, Iowa
- Technology
- Wind: 80.0 MW
- Total requested
- 80.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 11 April 2003
- Agreement signed
- 23 December 2009
- Proposed online date
- July 2006
- Came online
- July 2006
Location
Marker shows the centre of Pocahontas County; the queue data does not give exact sites.
Other requests in Pocahontas County
- Solar project J3137, Pocahontas CountySolar · 156 MW · in study
- Other project GI-1201, Pocahontas CountyOther · 7.0 MW · built
- Onshore wind project T93, Pocahontas CountyOnshore wind · 1,500 MW · withdrawn
- Onshore wind project T92, Pocahontas CountyOnshore wind · 1,500 MW · withdrawn
- Onshore wind project J2481, Pocahontas CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J1978, Pocahontas CountyOnshore wind · 175 MW · withdrawn
- Onshore wind project G315, Pocahontas CountyOnshore wind · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem