United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J1978, Pocahontas County

Onshore wind project J1978, Pocahontas County is a 175 MW onshore wind request withdrawn in the MISO interconnection queue, in Pocahontas County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1978
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Lemars Tap-Little Sioux 161kV
Location
Pocahontas County, Iowa
Technology
Wind: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 August 2021
Proposed online date
October 2025
Withdrawn
October 2025

Location

Marker shows the centre of Pocahontas County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Pocahontas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem