πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project G957, Emmet County

Onshore wind project G957, Emmet County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G957
Grid region
MISO (Midcontinent)
Connection point (POI)
Winnco Corner 161 Substation
Location
Emmet County, Iowa
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
23 January 2008
Agreement signed
26 July 2012
Proposed online date
December 2010
Withdrawn
July 2012

Location

Marker shows the centre of Emmet County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Emmet County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem