ONSHORE WIND Β· MISO

Onshore wind project G730, Emmet County

Onshore wind project G730, Emmet County is a 73.5 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandonedApr 2007 (project stopped here)
  3. ConsentedApr 2007 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G730
Grid region
MISO (Midcontinent)
Connection point (POI)
Maple Swtich Station
Location
Emmet County, Iowa
Technology
Wind: 73.5 MW
Total requested
73.5 MW
Queue status
Withdrawn
Entered queue
29 January 2007
Agreement signed
23 April 2007
Proposed online date
July 2008
Withdrawn
April 2007

Location

Marker shows the centre of Emmet County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Emmet County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem