ONSHORE WIND Β· MISO

Onshore wind project G552, Emmet County

Onshore wind project G552, Emmet County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2005 (completed)
  2. Withdrawn / abandonedApr 2010 (project stopped here)
  3. ConsentedApr 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G552
Grid region
MISO (Midcontinent)
Connection point (POI)
Maple Hill Substation 69 kV
Location
Emmet County, Iowa
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
28 September 2005
Agreement signed
6 April 2010
Proposed online date
June 2006
Withdrawn
April 2010

Location

Marker shows the centre of Emmet County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Emmet County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem