ONSHORE WIND Β· MISO

Onshore wind project J439, Emmet County

Onshore wind project J439, Emmet County is a 500 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2015 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J439
Grid region
MISO (Midcontinent)
Connection point (POI)
Dickens, IA 51333 at O'Brien to Kossuth 345 kV
Location
Emmet County, Iowa
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
16 March 2015
Proposed online date
December 2016
Withdrawn
October 2018

Location

Marker shows the centre of Emmet County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Emmet County