ONSHORE WIND Β· MISO

Onshore wind project J462, Emmet County

Onshore wind project J462, Emmet County is a 598 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2015 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J462
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Emmet County, Iowa
Technology
Wind: 598 MW
Total requested
598 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
18 May 2015
Proposed online date
September 2016
Withdrawn
June 2016

Location

Marker shows the centre of Emmet County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Emmet County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem