United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J462, Emmet County
Onshore wind project J462, Emmet County is a 598 MW onshore wind request withdrawn in the MISO interconnection queue, in Emmet County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2015 (completed)
- Withdrawn / abandonedJun 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J462
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Emmet County, Iowa
- Technology
- Wind: 598 MW
- Total requested
- 598 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 18 May 2015
- Proposed online date
- September 2016
- Withdrawn
- June 2016
Location
Marker shows the centre of Emmet County; the queue data does not give exact sites.
Other requests in Emmet County
- Onshore wind project J439, Emmet CountyOnshore wind Β· 500 MW Β· withdrawn
- Onshore wind project G957, Emmet CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G614, Emmet CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2017-025, Emmet CountyOnshore wind Β· 74.0 MW Β· withdrawn
- Onshore wind project G730, Emmet CountyOnshore wind Β· 73.5 MW Β· withdrawn
- Onshore wind project G552, Emmet CountyOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem