United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J342, Buchanan County

Onshore wind project J342, Buchanan County is a 305 MW onshore wind request withdrawn in the MISO interconnection queue, in Buchanan County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2014 (completed)
  2. Withdrawn / abandonedAug 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J342
Grid region
MISO (Midcontinent)
Connection point (POI)
345 kV substioin on Hazleton - Arnold line
Location
Buchanan County, Iowa
Technology
Wind: 305 MW
Total requested
305 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
19 May 2014
Proposed online date
August 2015
Withdrawn
August 2014

Location

Marker shows the centre of Buchanan County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Buchanan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem