United States › Grid › Interconnection queues › Iowa
BATTERY STORAGE · MISOBattery storage project J3780, Buchanan County
Battery storage project J3780, Buchanan County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Buchanan County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3780
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Hazleton
- Location
- Buchanan County, Iowa
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Buchanan County; the queue data does not give exact sites.
Other requests in Buchanan County
- Battery storage project J2545, Buchanan CountyBattery storage · 200 MW · in study
- Other project G220, Buchanan CountyOther · 650 MW · withdrawn
- Gas project G181, Buchanan CountyGas · 600 MW · withdrawn
- Gas project G182, Buchanan CountyGas · 600 MW · withdrawn
- Other project G159, Buchanan CountyOther · 500 MW · withdrawn
- Onshore wind project J1341, Buchanan CountyOnshore wind · 398 MW · withdrawn
- Onshore wind project J342, Buchanan CountyOnshore wind · 305 MW · withdrawn
- Other project G653d, Buchanan CountyOther · 23.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem