Onshore wind project J1427, Benton County

Onshore wind project J1427, Benton County is a 400 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Iowa, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1427
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Duane Arnold 345kV Substation
Location
Benton County, Iowa
Technology
Wind: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
August 2022
Withdrawn
March 2021

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem