United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J610, Benton County
Onshore wind project J610, Benton County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJun 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J610
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Benton County, Iowa
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- September 2018
- Withdrawn
- June 2017
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Other requests in Benton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem