United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J610, Benton County

Onshore wind project J610, Benton County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Benton County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J610
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Benton County, Iowa
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
September 2018
Withdrawn
June 2017

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem