United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2025 requests) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 9 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Dry Creek Solar II
Solar · Oak Hill Solar II LLC
302 MWIn study Rusk, TXERCOT Jun 2025target 2028
Badger Solar
Solar + storage · 174 Power Global Properties, LLC
302 MWIn study Upton, TXERCOT Feb 2025target 2029
Dairyland Storage
Battery storage · ENGIE IR Holdings LLC
302 MWIn study Hopkins, TXERCOT Apr 2025target 2029
Cazadores Solar
Solar · OCI Energy LLC
302 MWIn study Duval, TXERCOT Jul 2025target 2029
Soluce Bravo Storage
Solar + storage · BNPB1, LLC
302 MWIn study Brown, TXERCOT Jan 2025target 2028
Galaxy Solar 2
Solar · Galaxy Solar 2, LLC
302 MWIn study Ellis, TXERCOT Jun 2025target 2029
Simsboro Storage
Battery storage · Simsboro Storage LLC
302 MWIn study Freestone, TXERCOT Jun 2025target 2029
Gulf Gateway Storage One
Solar + storage · Gulf Gateway Storage, LLC
301 MWIn study San Patricio, TXERCOT Aug 2025target 2027
Gulf Gateway Solar One
Solar + storage · Gulf Gateway Solar, LLC
301 MWIn study San Patricio, TXERCOT Apr 2025target 2027
Cenizo Solar
Solar · Renew Development Holdco, LLC
301 MWIn study Webb, TXERCOT Nov 2025target 2029
Cernan BESS
Battery storage · Scarlet BESS LLC
301 MWIn study Wharton, TXERCOT Feb 2025target 2027
Sweetheart Solar
Solar + storage · Sweetheart Energy, LLC
301 MWIn study Young, TXERCOT Aug 2025target 2029
Prairie Branch Solar
Solar + storage · Prairie Branch Solar
301 MWIn study Montague, TXERCOT Sep 2025target 2028
Blue Spring Solar
Solar · Flat Creek Solar, LLC
301 MWIn study Haskell, TXERCOT Oct 2025target 2028
Sundance Solar
Solar · Sundance Solar, LLC
301 MWIn study Knox, TXERCOT Apr 2025target 2029
Apricot Sun Storage
Solar + storage · Apricot Sun Energy Center, LLC
301 MWIn study Duval, TXERCOT Apr 2025target 2029
Barranca Wind 1
Onshore wind · Barranca Wind Energy, LLC
301 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Honeybee Solar, LLC
Solar · Honeybee Solar Energy, LLC
301 MWIn study Brunswick, VAPJM Jan 2025target 2025
Other project 977298, Wake County
Other
300 MWIn study Wake, NCSoutheast Jun 2025
Solar project J3957, Sullivan County
Solar
300 MWIn study Sullivan, MOMISO Apr 2025target 2029
Onshore wind project 763, Power County
Onshore wind
300 MWIn study Power, IDWest Mar 2025target 2030
Battery storage project J3006, Milwaukee County
Battery storage
300 MWIn study Milwaukee, WIMISO Jul 2025target 2028
Solar project GEN-2024-316, Atoka County
Solar
300 MWIn study Atoka, OKSPP Mar 2025target 2030
WMA300SB
Solar + storage
300 MWIn study Sierra, NMWest May 2025target 2029
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Solar + storage project 772, Elmore County
Solar + storage
300 MWIn study Elmore, IDWest Apr 2025target 2030
Gas project S0035, Washington County
Gas
300 MWIn study Washington, UTWest Apr 2025target 2027
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Gas project GEN-2024-254, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Solar project GI-CS-2025-05, Weld County
Solar
300 MWIn study Weld, COWest Sep 2025target 2029
Solar project J3884, Benton County
Solar
300 MWIn study Benton, MNMISO Feb 2025target 2030
Battery storage project T2-075, San Juan County
Battery storage
300 MWIn study San Juan, UTWest Sep 2025target 2027
Solar project GEN-2024-099, Castro County
Solar
300 MWIn study Castro, TXSPP Mar 2025target 2031
Battery storage project J3946, Tazewell County
Battery storage
300 MWIn study Tazewell, ILMISO Mar 2025target 2030
Onshore wind project J3901, Shelby County
Onshore wind
300 MWIn study Shelby, ILMISO Jan 2025target 2030
Solar + storage project GEN-2024-113, Sequoyah County
Solar + storage
300 MWIn study Sequoyah, OKSPP Mar 2025target 2028
Battery storage project J4095, Huron County
Battery storage
300 MWIn study Huron, MIMISO Oct 2025target 2030
Solar project J4074, Crittenden County
Solar
300 MWIn study Crittenden, ARMISO Sep 2025target 2029
Onshore wind project GEN-2024-240, Nowata County
Onshore wind
300 MWIn study Nowata, OKSPP Mar 2025target 2029
Battery storage project AH1-260, Camden County
Battery storage · Haddy Energy Storage LLC
300 MWIn study Camden, NJPJM Jan 2025target 2025
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Battery storage project J4016, Tuscola County
Battery storage
300 MWIn study Tuscola, MIMISO May 2025target 2029
Solar project 25-00381, Lassen County
Solar
300 MWIn study Lassen, CAWest Jul 2025target 2029
Solar project GEN-2024-226, Hempstead County
Solar
300 MWIn study Hempstead, ARSPP Mar 2025target 2030
Battery storage project GEN-2024-230, Wilbarger County
Battery storage
300 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Bendito Wind
Onshore wind · Bendito Wind Farm, LLC
300 MWIn study Webb, TXERCOT Jul 2025target 2029
Solar project J4196, Phillips County
Solar
300 MWIn study Phillips, ARMISO Sep 2025target 2029
Solar + storage project GI-2025-02, Cheyenne County
Solar + storage
300 MWIn study Cheyenne, COWest Apr 2025target 2030
Solar + storage project J3114, Greene County
Solar + storage
300 MWIn study Greene, INMISO Nov 2025target 2026
Page 9 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)