🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Utah

GAS · WEST

Gas project S0035, Washington County

Gas project S0035, Washington County is a 300 MW gas request in interconnection study in the West interconnection queue, in Washington County, Utah, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S0035
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Red Butte Three Peaks Sigurd transmission line
Location
Washington County, Utah
Technology
Gas: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
1 April 2025
Proposed online date
December 2027

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem