Solar project 737, Washington County

Solar project 737, Washington County is a 122 MW solar request built and operating in the West interconnection queue, in Washington County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. ConsentedJun 2018 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
737
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Cove Mountain Solar 2, LLC
Connection point (POI)
Enterprise Valley substation
Location
Washington County, Utah
Technology
Solar: 122 MW
Total requested
122 MW
Service type
Energy only (ERIS)
Study phase
IA signed 6/25/18
Queue status
Operational
Entered queue
15 April 2016
Agreement signed
25 June 2018
Proposed online date
October 2020

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem