United States › Grid › Interconnection queues › Missouri
SOLAR · MISOSolar project J3957, Sullivan County
Solar project J3957, Sullivan County is a 300 MW solar request in interconnection study in the MISO interconnection queue, in Sullivan County, Missouri, connecting to AMEREN MISSOURI.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3957
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- Other_
- Location
- Sullivan County, Missouri
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 17 April 2025
- Proposed online date
- November 2029
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Solar project E0013, Sullivan CountySolar · 310 MW · in study
- Solar project J3958, Sullivan CountySolar · 300 MW · withdrawn
- Onshore wind project GI-46, Sullivan CountyOnshore wind · 88.8 MW · withdrawn
- Onshore wind project GI-64, Sullivan CountyOnshore wind · 77.5 MW · withdrawn
- Onshore wind project GI-49, Sullivan CountyOnshore wind · 77.5 MW · withdrawn
- Onshore wind project GI-56, Sullivan CountyOnshore wind · 77.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem