United States βΊ Grid βΊ Interconnection queues βΊ Missouri
ONSHORE WIND Β· SOUTHEASTOnshore wind project GI-49, Sullivan County
Onshore wind project GI-49, Sullivan County is a 77.5 MW onshore wind request withdrawn in the Southeast interconnection queue, in Sullivan County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-49
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Hickory Creek to Locust Creek 161 kV line
- Location
- Sullivan County, Missouri
- Technology
- Wind: 77.5 MW
- Total requested
- 77.5 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 24 June 2013
- Proposed online date
- June 2014
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Solar project E0013, Sullivan CountySolar Β· 310 MW Β· in study
- Solar project J3957, Sullivan CountySolar Β· 300 MW Β· in study
- Solar project J3958, Sullivan CountySolar Β· 300 MW Β· withdrawn
- Onshore wind project GI-46, Sullivan CountyOnshore wind Β· 88.8 MW Β· withdrawn
- Onshore wind project GI-64, Sullivan CountyOnshore wind Β· 77.5 MW Β· withdrawn
- Onshore wind project GI-56, Sullivan CountyOnshore wind Β· 77.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem